Below is the Nuclear Regulatory Commission's review schedule for the Three Mile Island Unit 1 license renewal application.

Receive license renewal application
Jan. 8, 2008
 
Publish Federal Register Notice (FRN) - license renewal application availability
Jan. 31, 2008
 
Public Meeting - license renewal overview
March 4, 2008
 
Publish FRN - acceptance/rejection and opportunity for hearing
March 14, 2008
 
Publish FRN - Environmental Scoping meeting
March 28, 2008
 
Audit - Environmental
April 28, 2008
 
Public Meeting - Environmental Scoping
May 1, 2008
 
Deadline for filing hearing requests and petitions for intervention
May 13, 2008
 
Audit - Scoping and Screening audit methodology
May 19, 2008
 
Environmental scoping period ends
May 30, 2008
 
Audit - Aging Management Programs
July 28, 2008
 
Issue draft Supplemental Environmental Impact Statement (SEIS)
Dec. 2, 2008
 
Publish FRN - draft SEIS available for comments
Dec. 12, 2008
 
Public Meeting - draft SEIS meeting
Feb. 24, 2009
 
Issue Safety Evaluation report with open items
March 13, 2009
 
End of draft SEIS comment period
March 4, 2009
 
Advisory Committee on Reactor Safeguards (ACRS) subcommittee meeting
April 1, 2009
 
Issue final Safety Evaluation report
June 30, 2009
 
Issue final SEIS
June 25, 2009
 
U.S. Environmental Protection Agency FRN published - availability of final SEIS
July 2, 2009
 
ACRS full committee meeting
Sept. 10, 2009
 
Decision on TMI Unit 1 license renewal
Oct. 22, 2009